Meta Signs PPA for Lightsource bp's 172 MW Mowata Solar Project in Louisiana

Key Facts

Capacity
172 MW
Location
Acadia Parish, Louisiana
Developer
Lightsource bp
Off-taker / Utility
Meta

Meta has signed a power purchase agreement for the full output of Mowata Solar, a 172 MW project being developed by Lightsource bp in Acadia Parish, Louisiana.

Deal context

This is the third PPA between Meta and Lightsource bp, bringing their combined contracted capacity to 545 MW. Meta says the project is expected to contribute more than $25 million to Chicot-area county revenue over its 30-year operating life, and the facility sits near Meta's broader data center investment in the region.

Timeline

Mowata Solar is expected to reach commercial operation in 2027, with full project completion targeted for 2028.